The Party Wall Act explained for extensions and loft conversions

The three kinds of notifiable work, how long notice you need to give, what happens after 14 days of silence, and what surveyors cost.

15 November 2026 · OJD Homes Ltd

What the Act is for

The Party Wall etc. Act 1996 sets out how you carry out certain building work next to a neighbour's property in England and Wales. It is separate from planning and building regulations. Having planning permission or a lawful development certificate does not cover it, and the council does not enforce it. If the Act applies and you start without serving notice, your neighbour can go to court to stop the work.

It matters most on semis and terraces, where loft conversions and rear extensions almost always touch a shared wall or dig near one.

The three kinds of notifiable work

  • Work to a party wall. Cutting in to take the bearing of a steel beam, inserting padstones, raising the wall for a loft conversion, cutting away a chimney breast, or rebuilding part of it. Two months' notice.
  • Excavation near a neighbour's foundations. Digging within 3 m of a neighbouring building where your foundations will go deeper than theirs, or within 6 m where your foundations would cut a line drawn down at 45 degrees from the bottom of theirs. One month's notice. Most rear extension foundations next to a neighbour's house fall into this.
  • A new wall on the boundary line. Building a wall up to or astride the boundary, for example the side wall of an extension. One month's notice. Building astride the boundary needs the neighbour's agreement.

Small jobs such as fixing shelves, replastering or adding sockets do not usually need notice. You can serve notice earlier than the minimum, and it lapses if the work has not started within a year.

Serving notice and the 14 days

Notice goes to every adjoining owner, which can mean the freeholder as well as the occupier. It must describe the work and, for excavation, include drawings showing where and how deep you will dig.

Talk to your neighbours before the notice arrives. A conversation and a copy of the drawings make consent more likely. Serve it early too: two months for party wall work can hold up the start of a loft conversion.

Your neighbour then has 14 days to respond. They can consent in writing, in which case you can go ahead once the notice period has run. They can dissent. If they do not reply at all within 14 days, a dispute is treated as having arisen, and the Act's surveyor process starts.

Surveyors and the award

Once there is a dispute, there are two routes.

  • An agreed surveyor. One surveyor acts for both sides, impartially. This is usually quicker and cheaper.
  • Two surveyors. You and your neighbour each appoint one. The two surveyors select a third surveyor at the start, who only steps in if they cannot agree.

The surveyors produce a party wall award. It sets out what work will be done, how and when, access arrangements, working hours and who pays. Either side can appeal to the county court within 14 days of receiving it. If your neighbour refuses to appoint a surveyor, you can serve a further notice and, after 10 days, appoint one on their behalf.

Who pays and what it costs

The building owner, meaning the person having the work done, usually pays all the surveyors' fees, including the neighbour's surveyor. Typical fees in Cheshire are £1,000 to £2,000 per neighbour. A mid-terrace loft conversion can mean two neighbours and two sets of fees. If the work damages the neighbour's property, the building owner has to put it right or pay for it.

Schedule of condition

Before work starts, the surveyor records the condition of the neighbour's side of the wall and any rooms likely to be affected, with notes and photographs. If cracks appear later, this is what everyone checks against. It protects you as much as your neighbour, because it shows which cracks were already there. It is worth doing even when your neighbour consents and no surveyor is appointed.

Next step

On a site visit we will tell you which parts of your extension or loft conversion are likely to need notice, and we build the notice periods into the written programme that comes with our fixed price.

About OJD Homes

OJD Homes Ltd is a building and property development company based in Northwich, Cheshire. It builds house extensions, loft and garage conversions, full renovations, kitchens, bathrooms and new builds across Cheshire, with a fixed price after a free site visit, and also buys probate, run-down and damaged houses for cash.

Building cost calculator

Services

Home extensionsLoft conversionsRenovationsGarage conversionsStructural workKitchens and bathroomsNew buildsLandlord refurbsInsurance repairsProbate sales

Builders by town

Builders in NorthwichBuilders in WinsfordBuilders in MiddlewichBuilders in KnutsfordBuilders in CreweBuilders in NantwichBuilders in ChesterBuilders in WarringtonBuilders in MacclesfieldBuilders in WilmslowBuilders in HartfordBuilders in SandbachBuilders in FrodshamBuilders in TarporleyBuilders in Holmes Chapel

Guides

How much does a loft conversion cost in Cheshire? 2026 pricesGarage conversion cost and planning: what you need to knowThe Party Wall Act explained for extensions and loft conversionsBuilding regulations for extensions: what you need to knowHow to choose a builder in Cheshire: checks before you signHow much does it cost to knock through a wall? 2026 guideSelling a probate house in Cheshire: the executor's step-by-step guideCan you sell a house before probate is granted?All guides →
Call 0333 038 3134Free quote